Calculate Critical Path

$
0
0
  Critical Path : “ The sequence of schedule activities that determines the duration of the project. It is the longest path through the project ” PMP Book 4th Edition , Page 431 Example   Activity Description Required Predecessor Duration A Product design (None) 5 months B Market research (None) 1 C Production analysis A [...]